56662 REL 12: 2009-001-00 EXP EXPANDED MULTI-SPECIES ACCLIMATION |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Produce and finalize plan for 2014 spring Chinook | B: 174. 2014 Multispecies rearing plan | 03/01/2014 | 03/01/2014 | |
Final Site List compliance for acclimation | C: 165. Final site list compliance for acclimation | 01/31/2015 | 01/31/2015 | |
All administrative tasks fulfilled with timely quality products | D: 119. Manage Expanded Acclimation Project | 01/31/2015 | 01/31/2015 | |
Stakeholder Coordination | E: 191. Coordination of Plan with Regional Stakeholders | 01/14/2015 | 01/14/2015 | |
Annual report to cover activities from 2/1/14 to 1/31/15 | F: 132. Annual synopsis report for 2014 contract year; developed as a technical memo or summary of findings | 01/30/2015 | ||
PIT tag spring Chinook and/or steelhead in the Methow basin | G: 158. Tag up to 24K spring Chinook and/or steelhead in the Methow basins for 2015 releases | 12/15/2014 | 12/15/2014 | |
acclimate spring Chinook in CY2014. | H: 176. Acclimate spring Chinook at Mid-Valley Pond | 05/15/2014 | 05/15/2014 | |
Continued development of Whitepine location (known now as Powerline) | I: 171. Develop additional site in Nason Creek for Wenatchee steelhead production | 01/31/2015 | 01/31/2015 | |
Development of a acc. site in the upper Methow and/or Chewuch | J: 171. Develop additional site in upper Methow and/or Chewuch for Methow steelhead and/or spring Chinook | 01/31/2015 | 01/31/2015 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered) |
|
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 02/01/2014 | ||||||
B | 174 | 2014 Multispecies rearing plan | 01/06/2014 | ||||||
C | 165 | Final site list compliance for acclimation | 02/01/2014 | ||||||
D | 119 | Manage Expanded Acclimation Project | 02/01/2014 | ||||||
E | 191 | Coordination of Plan with Regional Stakeholders | 02/01/2014 | ||||||
F | 132 | Annual synopsis report for 2014 contract year; developed as a technical memo or summary of findings | 02/01/2014 | ||||||
G | 158 | Tag up to 24K spring Chinook and/or steelhead in the Methow basins for 2015 releases | 02/03/2014 | ||||||
H | 176 | Acclimate spring Chinook at Mid-Valley Pond | 02/03/2014 | ||||||
I | 171 | Develop additional site in Nason Creek for Wenatchee steelhead production | 02/01/2014 | ||||||
J | 171 | Develop additional site in upper Methow and/or Chewuch for Methow steelhead and/or spring Chinook | 02/01/2014 |